Project Satu Mare 1 - Satu Mare County
Satu Mare County · Reference RDR-2026-008
Summary
49.5 MW PV - very close to RTB
Technical profile
- Project type
- PV
- PV capacity
- 49.5 MWp
- Development stage
- Permitting
- Land surface
- 46.5 ha
- Land rights
- Superficies (31y)
Grid connection
- Status
- Grid Connection Permit pending
- Voltage
- 110 kV
- Distance to grid
- ~ 9.0 km
Permits & consents
- Urbanism certificate (CU)
- Obtained
- Zoning plan (PUZ)
- Not Required
- Environmental
- Obtained
- Building permit
- Pending
- Natura 2000 overlap
- No
Description
This project is part of a portfolio of three photovoltaic projects located in the same area, in the extravilan of Satu Mare City, Satu Mare County.
The grid connection solution will be common for all three projects, through connection to a 110 kV substation located approximately 9 km away from the sites, by extending the existing substation.
The grid connection solution has already been approved by the local distribution operator (DEER) and is currently under approval by the Romanian transmission system operator, Transelectrica.
We estimate that the Grid Connection Approvals (ATRs) will be obtained within the next two months.
Regarding the building permit, all approvals have already been obtained except for the agricultural land conversion approval, which is currently in progress. We estimate that the project will obtain the building permit within a maximum of two months.
The project developers are also planning to add a BESS installation to each of the three photovoltaic parks.